| Production Process Production Process
Step 1 Clear the floor to be ready for the cement. However, the floor must contain with ferro-concrete. Its thickness is at least 10 cm. for car park in the house, surrounding area of the swimming pool and at least 15 cm. for the area with lots of weight to be put on such as the entrance road of villages, public car park, etc.
Step 2 Adjust the level of cement surface by applying with Morta cement over the ferro-concrete to make the surface even.
Step 3 Leave the concrete for a suitable time and then color and coat it with color hardener at the selected shade all over the area.
Step 4 Stamp the needed pattern onto the surface while the cement is not dry.
Step 5 Check details of the stamped pattern after the cement is dry. Clean the floor with a high pressure water jet. After it is all dry, cover the surface with 2 layers of acrylic chemical in order to make it stronger, to protect from water absorption and dust, and to prevent UV ray and moss for the easy maintenance. Also, it would make the stamped concrete have more deep color and clearer pattern.
|